Sub: Mana Badi Nadu-Nedu – Phase-II – Centrally Procured Materials – – Certain guidelines to deliver the products / Materials – Regarding.
Ref:
With reference to the above cited, tenders are finalized for certain items of Centrally Procured Materials for supply to Government schools (Educational Institutions) under Nadu-Nedu, Phase-II. Further indents are being received from the Head Master’s & AEs / ME’s of respective schools and accordingly products / items have to be delivered.
In this connection in continuation of the Circular issued vide reference 4th cited, certain guidelines are issued to delivery the products / items to the Government schools.
• Copper wire shall be supplied in the standard coils of 45.00 mtrs only of the requirement is more than 45.00 mtrs, the supply shall be in multiples of 45.00 mtrs.
• PVC conduit pipes shall be supplied in multiples of 3.00 mtrs as per the requirement.
• Small ftting such as Elbows, L-Bends, T-Bends, Ceiling roses shall be purchased locally of standard brands as per actual requirement for the school.
• Colour Legend for phase, Neutral & Earth is detailed below in the table.
S. No | Item | Phase / Neutral / Earth | Colour Legend | Remarks |
1 | 1.00 Sq.mm Copper wire | Earth | Green | Earth for Light and fan points |
2 | 1.50 Sq.mm Copper wire | Phase Neutral | Red Black | For light and fan points |
Earth | Green | Earth wire from distribution board to switch board | ||
3 | 2.50 Sq.mm copper wire | Phase Neutral | Blue Yellow | For Run of mains i.e. TPN / SPN to switch boards. |
4 | 4.00 Sq.mm Copper wire | Phase Neutral | Red Block | For Run of mains i.e. TPN to SPN & any A.C. points. |
Justification as area of treatment i.e. Deputy Executive Engineer of concerned Executive Engineer / Department shall inspect and certify the area quantity.
Sachivalayam Engineer from Mobile App shall take the photographs of area to be treated both for ceiling & top of roof slab before commencement of work and for every layer of treatment photograph shall be uploaded.
Local applicator shall not be engaged only company applicators are followed.
Before commencing the treatment on top of terrace roof any damaged to ceiling portion of roof shall be treated first and after completion of ceiling treatment terrace roof treatment shall be attended. Detailed specifications of water proofing to roof slab are kept in STMS Portal.
Surface Correction : Surface correction by rectifying surface undulations / slope corrections with Polymer (Latex) modified mortar.
• Coving : Coving the slab & Parapet wall corners and inner side of parapet wall surface with Polymer (Latex) modified mortar.
• Providing Rain : Ensure to provide spouts for draining rain water
• Water : Five layer system of water proofing treatment
Note:
• European Water Closet (EWC):
• One number for Girls change room
• One for WSN toilet (Differently abled person only)
• Orissa Pan with P or S trap size 580mm x 440mm:
• For High Schools – One number for every 40 students (Considering old existing toilets)
• Orissa Pan work P or S trap size 510mm x 400mm
• For Primary & Upper Primary schools – One number for every 40 students (considering old existing toilets)
• Hand Wash Basin:
• Minimum one number for each toilet block of Girls & Boys.
• However, depending on strength of students number may be increased as per availability of space inside toilet block and requirement as per strength.
• CP Short body Bib Cocks, 12.70mm diameter:
• One number for each water closet (IWC) room.
• CP Long body Bib cocks, 12.70mm diameter:
• For hand wash station / cistern depending on strength student.
• Heavy duty fush cock:
• Shall be indented depending on number of Indian water closets (IWCs) in the school (considering new & old IWCs) one number for each water closet.
• Urinal bowl of size (440mm x 265mm x 315mm) for Boys:
• One number for every 20 students (Boys).
• Squatting fat back Urinal for Girls:
• For Primary Schools only.
• One number for every 20 students (Girls)
• Flush cocks for IWCs and Squatting fat back Urinals shall be fxed before plastering to walls and before laying tiles to the walls along with water supply lines.
The above guidelines shall be followed as per necessity and functional utility.
NMMS MODEL GRAND TEST - 9NMMS MODEL GRAND TEST - 9HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 8NMMS MODEL GRAND TEST - 8HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 7NMMS MODEL GRAND TEST - 7HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 6NMMS MODEL GRAND TEST - 6HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 5NMMS MODEL GRAND TEST - 5HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 4NMMS MODEL GRAND TEST - 4HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 3NMMS MODEL GRAND TEST - 3HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 2NMMS MODEL GRAND TEST - 2HOW TO ATTEMPT AP NMMS… Read More
NMMS MODEL GRAND TEST - 1 NMMS MODEL GRAND TEST - 1 HOW TO ATTEMPT… Read More
'PAPER CUTTING' NMMS MENTAL ABILITY ONLINE TESTS re you preparing for the NMMS exam? Do… Read More